Lesson

Conduct systems engineering process improvement reviews in order to identify, prioritize, and refine systems engineering processes.

Florida DOT's experience in performing systems engineering process improvement reviews.


4/1/2006
Florida,United States


Background (Show)

Lesson Learned

A final report for the SE process improvement review was completed in April of 2005. The report provides descriptions of the successful SE applications, areas where the application of SE needs improving, prioritized recommendations, and various lessons learned in the deployment of ITS. Florida's SE process review experience provides the following guidance:
  • Be rigorous in preparing and refining SE documentation. Systems engineering is recognized as an effective way to document and transfer knowledge about the project among project personnel. This becomes more obvious when there is a change in the project management and/or technical staffing.
  • Keep your Regional Architecture documentation up to date. Information in a Regional Architecture can be used as a baseline for ITS project development, so it is important to keep architecture documentation updated. If the Regional Architecture documentation is not maintained, then subsequent projects may not include key functionalities or data flows.
  • Conduct independent Quality Assurance/Quality Control (QA/QC) reviews. Independent QA/QC reviews may help migrate some of the risks that a project experiences due to differences between the Technical Special Provisions and procurement specifications. One Florida DOT District developing a Transportation Management Center addressed these issues as lessons learned for future projects by meeting with design teams to perform document continuity checks as part of the QA/QC process.
  • Conduct post-project reviews to help refine the application of SE and the associated organizational processes. Post-project reviews help document lessons learned and direct needed refinements to the defined SE process.
  • Seek clarity on SE concepts through available resources. Multiple resources for the explanation of systems engineering concepts are openly available on the Internet. The application of systems engineering may vary slightly among domains, however the basic concepts remain the same.
  • Conduct periodic SE process improvement reviews. Systems engineering process reviews help identify and prioritize needs for successful implementation of SE. Process reviews are also a good way to collect lessons learned so the SE process can be refined.
The SE process improvement review discussed above was FDOT's second such review in four years. Florida has found that process improvement reviews help to identify SE priorities for a rapidly evolving ITS program. As a result, FDOT is able to justify and prioritize funding and other resources to advance SE capabilities within their program.

Systems engineering is a user-needs driven process and provides tools to measure user/customer satisfaction. In addition, SE practices are designed to simplify complex processes while maximizing work productivity. These outcomes allow FDOT to foster the goals of increasing customer satisfaction and improving productivity.


Lesson Comments

No comments posted to date

Comment on this Lesson

To comment on this lesson, fill in the information below and click on submit. An asterisk (*) indicates a required field. Your name and email address, if provided, will not be posted, but are to contact you, if needed to clarify your comments.



Source

Florida ITS Systems Engineering Process Improvement Review: Final Report and Recommendations

Published By: Federal Highway Administration - Florida Division & Florida Department of Transportation ITS Office

Source Date: 4/1/2006

Lesson Contacts

Lesson Contact(s):

Dawn Hardesty
Noblis
202-863-3648
dhardesty@noblis.org


Agency Contact(s):

Chung Tran
FHWA, Florida Division
850-942-9650
chung.tran@fhwa.dot.gov

Lesson Analyst:

Firoz Kabir
Noblis
202-863-2987
firoz.kabir@noblis.org


Rating

Average User Rating

0 ( ratings)

Rate this Lesson

(click stars to rate)

Application Areas

None defined

States

Florida

Countries

United States

Focus Areas

None defined

Keywords

None defined

Lesson ID: 2006-00283