Lesson

Determine agency capability level when selecting the most appropriate ITS procurement package.

Experience from a review of ITS contracting methods and practices. Step 4 of the Decision Model.


2006
United States


Background (Show)

Lesson Learned

In addition to project complexity and risk, another factor critical to the selection of an appropriate procurement package is the agency's organization, experience, and resources relative to ITS procurements. The fourth step in the Decision Model for contracting ITS projects involves an honest assessment of the agency's capabilities. Major ITS projects with significant software development, hardware integration and long-term operations and maintenance support require sufficient agency capabilities; otherwise, the project risks not being successful. If an agency does not have the resources or organization for handling a major ITS project, it should consider reducing the scope of the project, seeking additional consultant services, or not doing the project.

The guide defines three agency capability levels (levels 1, 2 and 3) based on an assessment of six factors: personnel experience, organizational experience and structure, resources, management support, and agency expectations. Each of these factors has an impact on the success of an ITS project implementation. The following observations are made with regard to evaluating an agency’s capabilities:
  • Assess personnel experience. Agencies must assess the level of staff support dedicated to ITS projects as well as the staff’s previous experience with ITS. For example, agencies with no staff support and little to no prior ITS experience are characterized as level 1. At the other extreme, agencies with a full-time ITS manager and staff with significant ITS experience are classified as level 3.
  • Assess organizational experience. Organizational experience is based on an agency's experience with complex and risky projects (i.e. project categories). An agency that has had no previous ITS experience, or has only administered a category 1 project (straightforward and low risk) is characterized as level 1, whereas an agency with experience on at least one category 3 project (complex and high risk) is classified as level 3.
  • Assess Organizational Structure. For this factor, the agency must assess the extent to which it is organized to support ITS projects. In Level 3 agencies, for example, responsibility for ITS is clearly defined and housed within a specific organizational unit within the agency.
  • Evaluate Resources. Agencies need to evaluate whether their organization has an identifiable budget for ITS. If there is little to no funding for ITS, the agency is classified as level 1, whereas a level 3 agency has an identifiable budget set aside for ITS.
  • Assess Management support. This factor addresses the extent to which ITS and Operations are considered a priority within an agency and the level of interest in ITS at top management levels. Agencies receiving a higher classification level have top management support and consider ITS to be a priority.
  • Determine Expectations. Agencies with no defined expectations are classified as level 1, whereas level 3 agencies have included ITS /Operations in both their short and long range planning; expectations are well-defined and based on actual performance measures.
As with the categorizing of projects, the categorizing of agencies may not be clear-cut. The guide recommends that personnel and organizational experience receive the greatest weight. If an agency appears to fit equally well within two different levels, the lower level should be selected.

Upon identifying the project category level and the agency capability level, the agency can then proceed to the selection of the systems engineering process and the identification of the appropriate procurement package(s). The guide uses these two critical factors in its decision matrix for selecting procurement packages. These steps of the Decision Model are designed to create an efficient and reliable procurement process. This increased efficiency can result in cost savings for agencies in the procurement of ITS. Moreover, by enabling agencies to choose the most appropriate procurement package, the Decision Model facilitates the ultimate success of the ITS deployment.


Lesson Comments

No comments posted to date

Comment on this Lesson

To comment on this lesson, fill in the information below and click on submit. An asterisk (*) indicates a required field. Your name and email address, if provided, will not be posted, but are to contact you, if needed to clarify your comments.



Source

Guide to Contracting ITS Projects

Author: Kenneth R. Marshall and Philip J. Tarnoff

Published By: National Cooperative Highway Research Board

Source Date: 2006

Other Reference Number: NCHRP Report 560

URL: http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_560.pdf

Other Lessons From this Source

Lesson Contacts

Lesson Contact(s):

Kenneth R. Marshall
Edwards & Kelcey
410-747-3420
KMarshall@ekmail.com

Phil Tarnoff
University of Maryland
301-403-4619
tarnoff@eng.umd.edu

Lesson Analyst:

Margaret Petrella
U.S. DOT/ RITA The Volpe National Transportation Systems Center
617-494-3582
petrella@volpe.dot.gov


Rating

Average User Rating

3 (1 rating)

Rate this Lesson

(click stars to rate)


Lesson ID: 2007-00324