Take advantage of time-specific opportunities to organize and build support for a formal incident management program.

Major metropolitan areas' experiences with formalized incident management programs.


5/1/2001
Atlanta,Georgia,United States; Houston,Texas,United States; Seattle,Washington,United States; Milwaukee,Wisconsin,United States; Chicago,Illinois,United States; Los Angeles,California,United States; San Francisco,California,United States; Detroit,Michigan,United States; San Antonio,Texas,United States; Maryland,United States


Background (Show)

Lesson Learned

The Regional Traffic Incident Management Programs: Implementation Guide aims to explain general steps to implementation (with an institutional, rather than technical, focus), and is based on understanding needs, defining the program, building and maintaining support, assessing the program’s effectiveness, and revising its approach to better address the needs. The following two lessons are based on the experience of others regarding building program support for a formal incident management program:
  • Take advantage of attention focused on major events (international games, weather events, earthquakes, etc.) to help organize and build support for a formal incident management program. While some of these events cannot be anticipated, it is important to set the stage for success. Begin organizing interagency working groups and building the case for a program prior to a major event or crisis. Then, once an event occurs, take advantage of the media attention and public outcry to focus attention and resources on organizing a coordinated incident management program. In other words, strike while the iron is hot!

    As an example, in the 1970s the GDOT Commissioner tried and failed to organize an interagency incident management program. It wasn’t until 1992 that the Chief of Georgia’s Emergency Management Agency (GEMA) began to include law enforcement and GDOT in emergency response. However, it was the announcement that Atlanta would host the 1996 Summer Olympics that was the real catalyst for mobilization. The GDOT Director of Operations helped organize the program because of his experience and his relationships within his agency. Critical to the success of this effort was the identification of a "credible nucleus" that recognized that many agencies had a role in managing incidents. In Georgia, this was GEMA. While it is important to understand that agencies cannot be forced to work together, if a viable framework is in place, a major event can help mobilize and solidify support for a coordinated interagency program. Steve Parks, Deputy Commissioner, Georgia Department of Transportation (GDOT), said, "You cannot wait for a crisis or international event to occur before organizing incident management agencies. Start the program and dialogue prior to any event, and the event will help solidify those relationships."

  • Obtain and leverage political support when it is available. Since transportation funding is often politically influenced and transportation policy is an important item on political agendas, support of political leaders for transportation projects is essential. Obtaining political support is particularly important for incident management programs since they do not offer publicity-laden opportunities such as ribbon-cutting ceremonies for new roads or bridges. Obtaining political support is an important step for the success and sustainability of any incident management program. This step requires informing leaders about the benefits of incident management and convincing them of the need for a formal program.

    It also can be accomplished by taking advantage of scenarios such as this one, in Houston: Mayor Lanier of Houston encountered severe traffic congestion on the way to a Houston Oilers football game. He called his staff several times, but no one could give him accurate information about what was happening or how long the congestion might last. He reached the game close to half-time. The next day he initiated action to ensure that his experience would not be repeated by Houston-area citizens. Thus, the Houston area’s first incident management program and the Houston TranStar ITS system were born. The mayor, a previous member of the State Transportation Board, led an effort to gain the cooperation of the other agencies in the Houston area. His efforts enabled TxDOT, Houston METRO, and the Houston Police Department to gain top management buy-in for their portions of the incident management program. The result was an incident management program developed in a very short time.

Two ways of improving an incident management program include taking advantage of the media and public attention given to large events, and seeking out political support of the program. In this way, incident management programs will become more organized, structured, and the opportunity for program sustainability will be enhanced, improving mobility and customer satisfaction.


Lesson Comments

No comments posted to date

Comment on this Lesson

To comment on this lesson, fill in the information below and click on submit. An asterisk (*) indicates a required field. Your name and email address, if provided, will not be posted, but are to contact you, if needed to clarify your comments.



Source

Regional Traffic Incident Management Programs: Implementation Guide

Author: Vincent Pearce

Published By: U.S. Department of Transportation, FHWA ITS Joint Program Office, Federal Transit Administration

Source Date: 5/1/2001

EDL Number: 13149

Other Reference Number: FHWA-OP-01-002/FTA-TRI-11-00-03

URL: http://ntl.bts.gov/lib/jpodocs/repts_te/13149.pdf

Other Lessons From this Source

Lesson Contacts


Agency Contact(s):

David Helman
FHWA
202-366-8042
David.Helman@fhwa.dot.gov

Lesson Analyst:

Jane Lappin
Volpe National Transportation Systems Center
617-494-3692
jane.lappin@volpe.dot.gov


Rating

Average User Rating

0 ( ratings)

Rate this Lesson

(click stars to rate)


Application Areas

None defined

Countries

United States

Systems Engineering

Show the V

None defined

Focus Areas

None defined

Goal Areas

None defined

Keywords

None defined

Lesson ID: 2006-00177