Using current procedures, early CV deployer agencies overcome challenges concerning a general lack of CV technological maturity, evolving standards and policies and technological uncertainty regarding communication technologies in their procurement of connected vehicle devices.

Agencies provide feedback identified from interviewees and their experiences with CV procurement and deployment in Connected Vehicle Procurement State-of-the-Practice Report.



Background (Show)

Lesson Learned

CategoryLesson / Best Practice
New Partnerships and Policy
  • Partner with State DOT colleagues and their contracting expertise and consultants. This can help in selecting a vendor and ensuring the right consultant is used.
  • Work closely with the ITS JPO and refer to CV Pilot Documentation for city and state level CV projects.
  • Form good relationships with local universities and have intragovernmental agreements with them where possible. Universities can provide research and development for CV projects and may even be able to support initial testing of CV equipment.
  • For FCC licensing, use a state-level expert who understands the FCC licensing process. This can greatly reduce the time and effort needed to receive final FCC approval.
Category
Federal/Other CV Resources
  • Make use of CV resources offered by the ITS JPO, FHWA, National Operations Center of Excellence, AASHTO, etc.
    • Staff expertise
    • Model documentation (CV pilot program, SPaT challenge resources)
    • ITS Public Data Hub
    • Participate in CV/CAV -related peer exchanges
    • Take advantage of training opportunities (ITS PCB program, webinars)
Procurement and Project Resourcing
  • Prior to releasing an RFP to RSU vendors, hold a PlugFest to test vendor equipment with your signal equipment and controllers. This allows you to immediately see which vendors are truly interoperable which will be of great assistance when a final RFP is released.
  • For CV RFPs, it is suggested to have project requirements vetted by SMEs. This can help an agency contract with better qualified consultants and ultimately receive a better final product.
  • If possible, it is recommended to have on-site and off-site CV to support the CV project. Having that expertise can be an excellent resource to verify deliverable accuracy and ensure that the program goals and system requirements are being met.
  • Budget extra time for software development and equipment testing into your initial RFP.
  • Ensure that your contracting and procurement personnel are involved from the beginning of the project.
  • Consider viewing connected vehicle services through the lens of the service provider model. The service provider model offers more flexibility in choice of technologies and deployment strategies.
  • Make sure your procurement documentation has an approach to support future technology developments and standards.
Project Development Approach
  • Plan on using an agile approach to the software and application components of the CV project, while also using the traditional systems engineering approach where applicable.
  • Use a systems manager approach with a lump sum fixed priced contract for the CV work to help reduce risk and keep project costs in check.
  • Break the project up into smaller tasks (phased approach) can help complete the project more easily.
Contract Vehicles
  • Explore contractual options beyond your own agency’s that may be available to purchase CV equipment, such as statewide IT services and communications contracts; city, county, and regional contracts; and university contracts.



Lesson Comments

No comments posted to date

Comment on this Lesson

To comment on this lesson, fill in the information below and click on submit. An asterisk (*) indicates a required field. Your name and email address, if provided, will not be posted, but are to contact you, if needed to clarify your comments.



Source

Connected Vehicle Procurement State of the Practice Assessment: Summary Findings Report (Final)

Author: Hatcher, Greg; Jason Campos; John Craig; and Dawn Hardesty

Published By: USDOT Federal Highway Administration

Other Reference Number: FHWA-JPO-18-703

URL: https://www.google.com/search?source=hp&ei=Zs3-W9JVxNTmArGytjA&q=FHWA-JPO-18-703&btnK=Google+Search&oq=FHWA-JPO-18-703&gs_l=psy-ab.3...130667.130667..131843...0.0..0.72.72.1......0....1j2..gws-wiz.....0.PUclylprSV8

Lesson Contacts

Lesson Analyst:

Kathy Thompson


Rating

Average User Rating

0 ( ratings)

Rate this Lesson

(click stars to rate)


Lesson Categories

Procurement > Work Allocation

States

None defined

Countries

None defined

Systems Engineering

Show the V

None defined

Focus Areas

None defined

Keywords

None defined

Lesson ID: 2018-00842