Source: Lessons Learned from the Irvine Integrated Freeway Ramp Metering/ Arterial Adaptive Signal Control Field Operational Test

Establish the roles and responsibilities for overall management of the project at the onset, and alter the field operation test (FOT) process if needed.(January 2001)
Irvine, California's experience in managing a field operational test of an integrated Advanced Transportation Management System.

Choose proven technology and avoid changes to specifications.(January 2001)
Irvine, California's experience in implementing a field operational test of an integrated Advanced Transportation Management System.