Lesson
Develop a long-term ITS vision and use systems engineering processes to successfully manage ITS deployments.
Chattanooga Area Regional Transportation Authority's experience in deploying transit ITS
November 2009
Chattanooga,Tennessee,United States
Background (Show)
Lesson Learned
Before the start of the SmartBus project in 2003, the Chattanooga Area Regional Transportation Authority (CARTA) was not a heavy user of ITS technologies. The agency had computerized systems to support mostly back office operations, such as accounting, timekeeping, and payroll. The agency had a GIS software application to manage paratransit operations, though same-day reservations often had to be managed manually, and drivers used printed manifests to manage and record its routes. Fixed and flex route buses were equipped with fareboxes and headsigns, but operating these devices required considerable manual input from drivers. Incline Rail ticket sales were recorded in manual logs. Thus, a mixture of standalone applications and manual procedures were used to manage CARTA operations. With SmartBus project, CARTA successfully deployed ITS technologies to significantly automate the processes, integrate applications, and improve efficiency and productivity in agency’s operations and services. CARTA’s success story is summarized below.
- Develop a long-term vision for increased operational efficiency with the use ITS technologies. With the advent of the SmartBus project, CARTA envisioned an environment where manual processes were eliminated and data shared freely among applications. This would lead CARTA to automate many activities that previously required manual steps. It would also create a data-rich environment where CARTA could mine archived operations data to identify opportunities for improvement. For example, the integration of fuel usage and maintenance data through deploying and utilizing a data warehouse allowed CARTA to include both maintenance and fuel costs when assessing the cost-effectiveness of different fuels.
- Use systems engineering processes to manage ITS deployments. CARTA developed documents including, for example, a systems overview (concept of operations) plan that described its long-term vision for ITS and a systems engineering model with “V” processes tailored for CARTA. Various planning, process model, and design documents helped the agency keep track of its deployments and helped ensure that long lead-time activities were completed in time to support its future plans.
- Build a data warehouse early on to facilitate and manage ITS integration. CARTA developed a data warehouse early on. The presence of a data warehouse simplified CARTA’s other deployments in two ways. First, the data warehouse provided reporting tools, which eliminated the need for sophisticated reporting tools in individual CARTA applications. Second, applications could be integrated with the data warehouse, reducing the total number of interfaces that were required.
- Sequence deployments with consideration to mutual dependencies among applications and avoid temptation to do too much too fast. CARTA scheduled its deployments so that systems were deployed sequentially, avoiding deployment of dependent systems haphazardly or simultaneously. For example, one reason the CARTA data warehouse was its first ITS deployment was that so many other systems would need to integrate with it. Deploying it first meant that it could be operating stably before these other integrations occurred.
- Be flexible to accept schedule delays when needed to help manage deployment risks. When changes to CARTA's deployment schedule were needed, CARTA was willing to accept delays in order to control risks. For example, when the bus arrival time prediction system was deployed early to take advantage of an outside funding opportunity, CARTA delayed other deployment activities so as not to overburden its limited IT resources.
- Perform a through testing of the systems before introducing them to operations. CARTA displayed a strong commitment to thoroughly testing all systems before accepting them as complete and introducing them to operations. CARTA found and corrected many problems during final testing. If these problems had occurred in an operational system, they could have reduced the confidence of the public and CARTA management in the ITS plans.
States
Countries
Goal Areas
Keywords
None defined
Lesson ID: 2010-00556
Lesson Comments
No comments posted to date