Cost Subsystem
Unit Cost Element
Description

CCTV camera deployed as part of San Antonio's Freeway and Incident Management Expansion

Capital Cost Per Unit
$25,462.00
OM Cost Per Unit
$4,606.00
Adjusted Capital Cost Per Unit
$16,776.91
Adjusted O&M Cost Per Unit
$3,034.89
Reported Units
33
Unit Cost Type
Unit
Each (EA)
CPI ID
2
CPI Name

WPU1178

Year
1998
Notes
The project covered a 28.9-mile stretch of I-10, I-410, and US 281 in the northern region of San Antonio.