Unit Cost Entry

Unit Cost Element - Curve Speed Warning System

Unit Cost Component - Truck Curve Warning and High Wind Warning System for Bridge


Wenatchee, Washington, USA


Description

System consists of one large DMS with sign bridge, two small DMS with cantilever structure and bridge mounted support, loop detection, wind sensor/RWIS, and fiber and radio communications. Design and construction engineering costs ($85,000) included. Traffic control and mobilization also included.

Cost Type

Estimated

Data Date

2005

Reported Units



Units

Each (EA)

Year (Dollars)

2005

Capital Cost per Unit ($)

$572,000.00

O & M Cost per Unit ($)



Lifetime

20 years


Notes

Source

ITS Integration Program Unit Cost Data Collection Sheet: Vantage Truck/Wind Warning System - WA (FY03 Yr2)

Author: David Kieninger, Jennene Ring


Unit Cost Details

Capital Cost per Unit: $572,000.00

O&M Cost per Unit:

Year (Dollars): 2005

Lifetime: 20 years