Unit Cost Component
Description

$181 per square foot (ft2) [$181 per 0.0929 square meters (m2)] – The costs presented are based on the ITS Package C equipment deployment, including a 32,000 ft2 [2973 m2] SunGuideSM transportation management center (TMC).

Capital Cost Per Unit
$5,792,000.00
OM Cost Per Unit
$236,430.00
Adjusted Capital Cost Per Unit
$5,792,000.00
Adjusted O&M Cost Per Unit
$236,430.00
Lifetime
20
Unit Cost Type
Unit
Location
CPI ID
4
CPI Name

NDU BBLD-BBLD

Year
2003
Notes
FDOT District 6