Benefit

Dynamic outreach efforts in a construction workzone in Southern California reduce traffic volume by 20 percent and peak hour delay by 50 percent.

A 2004 project employs Automated Work Zone Information System (AWIS) and Quickchange Moveable Barrier (QMB) to benefit drivers traveling through construction zone.


31 July 2005
California,United States


Summary Information

This paper describes a multi-faceted outreach effort, as implemented in 2004 on the Interstate-15 (I-15) Devore urban highway reconstruction project in Southern California, to limit the negative impacts of construction closures on the traveling public. Overtime use of the facility has led to poor pavement conditions along on one of California's most heavily trafficked routes.

Methodology
Before the rehabilitation project ensued, It was essential to garner the support of the public due to the traffic disruption that would occur from round-the-clock construction. Thus, a well-devised and well-implemented public outreach program was undertaken to keep the public informed and to survey their feedback. As part of the interactive public outreach efforts, an I-15 Devore project website was launched that utilized an Automated Work Zone Information System (AWIS) to provide users with real-time travel and detour estimate information. Specifically, traffic count and speed data were monitored in key locations using remote traffic microwave sensor traffic surveillance units. Estimated travel times through the Construction Work Zone (CWZ) were also posted on permanent and variable message signs for motorists.

Travelers were further facilitated by the use of the Quickchange Moveable Barrier (QMB).The QMB served to provide dynamic lane configuration and was changed continuously to accommodate the direction of morning and afternoon commutes. This dynamic lane configuration under the QMB increased roadway capacity by favoring the rush hour direction of travel.

Results:

The overall inconvenience of reconstruction closures on traffic was mitigated due to diversion to detours, travel mode changes, and travel schedule adjustments encouraged through the use of AWIS and QMB technology. The traffic measurements study comparing traffic conditions before and during construction showed the following results:
  • Peak-hour traffic demand through the construction workzone was reduced by 20 percent.
  • Maximum peak-hour delay was reduced by 50 percent.

Benefit Comments

No comments posted to date

Comment on this Benefit

To comment on this summary, fill in the information below and click on submit. An asterisk (*) indicates a required field. Your name and email address, if provided, will not be posted, but are to contact you, if needed to clarify your comments.



Source

Dynamic Approach to Public Outreach for Minimizing Traffic Inconvenience in Urban Highway Rehabilitation

Author: Lee, Eul-Bum and Kunhee Choi

Published By: Paper Prepared for the 85th Annual Meeting of the Transportation Research Board

Source Date: 31 July 2005

URL: http://trid.trb.org/view.aspx?id=777104