Coordinate among stakeholders and schedule periodic team meetings to make sure that the correct and necessary information is provided for all development and implementation activities.
Lessons from the ICM Implementation Guide
February 2012
Background (Show)
Lesson Learned
After the critical design review (CDR) has been completed and the detailed design has been approved, system development and implementation, also known as build and test, can begin. At this point system components (hardware, software, mechanical devices, or even manual processes) can be built or developed per the approved detailed design document (DDD). Additionally, if commercial products are going to be used, they can now be purchased. After components are built, developed, or purchased they can then be tested, integrated, and implemented.
The following lessons learned apply to system development and implementation of an ICM program.
NOTE: Because the Pioneer Sites are in the early stages of systems operations of the ICMS, the build and tests lessons are still being developed; therefore, these lessons are excerpted from the Systems Engineering Guidebook for ITS section 5 – Case Studies Key Lessons. The three case studies included the New York City Transit Automatic Train Supervision system, the City of Baltimore Integrated Traffic Management System, and the Maryland CHART incident management.
The following lessons learned apply to system development and implementation of an ICM program.
- Develop prototypes that can be demonstrated with actual field equipment hardware and software. – The system should be demonstrated on an actual workstation mock-up.
- Provide an Independent Contractor Test Team. – Confirm adequate coverage in specifications to assure this standard development process protocol.
- Conduct operator training before testing is to begin. Conduct training early enough in the project to provide available and qualified resources to support testing activities.
- Test every change no matter how small. Thorough and realistic testing at every stage of system implementation, involving the owning agency in testing, and testing every change no matter how small and seemingly inconsequential, helps with progress monitoring and avoids expensive and time-consuming field retrofits.
- Use a qualified independent verification consultant. Using a qualified independent verification consultant was a contractual requirement of the agency and is felt to have been critical to the success that was achieved.
- Require strong system engineering qualifications of software contractors. The contract required that the software contractor have a solid history of using systems engineering and also required that the winning contractor bring its documented internal systems engineering processes to the project and train the agency in its use.
NOTE: Because the Pioneer Sites are in the early stages of systems operations of the ICMS, the build and tests lessons are still being developed; therefore, these lessons are excerpted from the Systems Engineering Guidebook for ITS section 5 – Case Studies Key Lessons. The three case studies included the New York City Transit Automatic Train Supervision system, the City of Baltimore Integrated Traffic Management System, and the Maryland CHART incident management.
States
None defined
Countries
None defined
Goal Areas
None defined
Keywords
None defined
Lesson ID: 2014-00673
Lesson Comments
No comments posted to date