Lesson
Recognize that deployment delays can lead to a ripple effect of challenges that affect project deployment progress.
Great Lakes ITS project management experience with deployment delays associated with the Airport ITS Integration Project.
2 March 2007
Detroit,Michigan,United States
Background (Show)
Lesson Learned
Although the federal portion of the ITS Earmark funding is nearly free from time constraints, time can be an unexpected adversary to the deployment of an ITS project. The Earmark funding is designated by Congressional action and as such the funds can remain unspent for many years until the funds are either expended or Congressional action rescinds the funds. While in some situations this may be beneficial, allowing state and local agencies time to make funding arrangements, procure hardware, et cetera, the passage of time can also lead to a ripple effect of challenges which can slow deployment progress.
Some of the deployment challenges experienced by those involved in the Airport ITS Integration project reveal the consequences of time passage. In FY2001, Southeast Michigan received the ITS Earmark in the DOT Appropriations Bill. In April 2002, the Wayne County Airport Authority became a separate agency managed by an independent, seven-member Board of Directors. The creation of a separate independent agency complicated the allocation of funding for the Airport ITS project (under Michigan state law the agency receiving the funds needed to be an eligible government county, city, or village agency to administer the highway funds). Consequently, alternative funding arrangements had to be investigated to identify a method to allow Wayne County to move funding to WCAA so that WCAA could complete their portion of the project. Then in January 2003, a new Wayne County Executive was elected and, as a result of a change in the political leadership, the Airport ITS project lost a key project leader at Wayne County. For several years little progress was made as the project had no champion to provide leadership to overcome the funding issue. While this was occurring, new priorities at WCAA resulted in new projects emerging, one of the largest of which was a $418 million new north terminal project announced in May 2006.
The following time related suggestions are based on the GLITS Airport ITS Integration project experience.
Some of the deployment challenges experienced by those involved in the Airport ITS Integration project reveal the consequences of time passage. In FY2001, Southeast Michigan received the ITS Earmark in the DOT Appropriations Bill. In April 2002, the Wayne County Airport Authority became a separate agency managed by an independent, seven-member Board of Directors. The creation of a separate independent agency complicated the allocation of funding for the Airport ITS project (under Michigan state law the agency receiving the funds needed to be an eligible government county, city, or village agency to administer the highway funds). Consequently, alternative funding arrangements had to be investigated to identify a method to allow Wayne County to move funding to WCAA so that WCAA could complete their portion of the project. Then in January 2003, a new Wayne County Executive was elected and, as a result of a change in the political leadership, the Airport ITS project lost a key project leader at Wayne County. For several years little progress was made as the project had no champion to provide leadership to overcome the funding issue. While this was occurring, new priorities at WCAA resulted in new projects emerging, one of the largest of which was a $418 million new north terminal project announced in May 2006.
The following time related suggestions are based on the GLITS Airport ITS Integration project experience.
- Keep in mind that the longer a project takes to be deployed the greater the likelihood the project will lose key personnel. In addition to leadership changes due to changes in the political environment, long delays can result in the loss of key personnel due to numerous other factors such as desire to change jobs, retirements, promotions, health considerations, etc.
- Be cognizant that the longer a project takes to be deployed the more likely stakeholder agencies could reorganize. Although probably less likely to occur than the loss of key personnel, the GLITS experience has shown that the reorganization of agencies can have a detrimental effect on the project deployment.
- Realize that stumbling blocks that produce long delays can put a project in competition with other high priority emerging projects. The long delay for the Airport ITS Integration project pushed the ITS related deployment activities into the civil construction activities scheduled for building the new $418 million north terminal. As a result, the Airport ITS Integration project will be required to share WCAA staff and coordinate time resources to avoid conflicts with the construction activities- a responsibility that was not foreseen several years ago.
Lesson Categories
States
Countries
Systems Engineering
Show the V
None defined
Goal Areas
Keywords
CCTV, closed circuit television cameras, road monitoring, sensors, vehicle detector, traffic detection, traffic monitoring, congestion monitoring
Lesson ID: 2006-00315
Lesson Comments
No comments posted to date