Benefit

In St. Louis County, Missouri, full closure of portions of I-64 for two years allowed for an accelerated construction schedule, saving taxpayers between $93 million and $187 million.

Results of The New I-64 Economic and Regional Mobility Study - Final Report.


November 2011
St. Louis County,St. Louis,Missouri,United States


Summary Information

In 2008 and 2009, large portions of the I-64 corridor west of St. Louis, Missouri were closed for construction in two separate phases that allowed for an accelerated construction timeline. The connectivity of the regional road network made the full closure of portions of the interstate possible without causing large increases in travel times or number of crashes. Missouri Department of Transportation (MoDOT) used an innovative set of tools, including alternative route mapping, in order to maintain high levels of customer satisfaction and public awareness of the project both before and during the closure.

Findings
  • By diverting 98,000 to 120,000 vehicles daily to alternative routes for two years, the impact costs over the normal operational state were $101.5 million.
  • Had a partial closure system been used, construction would have taken six to eight years and impact costs would have been between $147 million and $188.3 million (present value).
  • Assuming construction material costs remained consistent with inflation, the accelerated construction resulted in savings of between $93 million and $187 million.

Benefit Comments

No comments posted to date

Comment on this Benefit

To comment on this summary, fill in the information below and click on submit. An asterisk (*) indicates a required field. Your name and email address, if provided, will not be posted, but are to contact you, if needed to clarify your comments.



Source

The New I-64 Economic and Regional Mobility Study: Final Report

Author: Dr. Lance Gentry, M.B.A. Ph.D. Dr. Venkata Chilukuri, Ph. D. Thomas Hiles, EI Michael Trueblood, P.E., P.T.O.E. Christopher Kinzel, P.E. Robert Frazier, PE, AICP Dr. Ghulam Bham, Ph.D. Jonathan Lee Daniel Hodge Marissa Witkowski Tom Ryan, P.E.

Source Date: November 2011

URL: http://library.modot.mo.gov/RDT/reports/Ri07047/cmr12010.pdf

Rating

Average User Rating

0 ( ratings)

Rate this Benefit

(click stars to rate)


Benefit ID: 2012-00816