Unit Cost Element
Unit Cost Component
Description

Terminate Fiber in Cabinet (Install Labor)

Capital Cost Per Unit
$166.20
Adjusted Capital Cost Per Unit
$177.47
Reported Units
24
Unit Cost Type
Unit
Each (EA)
CPI ID
1
CPI Name

WPU1176

Year
2017
Notes
Project Description: Road and Bridge Reconstruction, Elgin O'Hare Western Access Tollway (IL 390) from West of Park Boulevard to East of Arlington Heights Road, M.P. 10.1 to M.P. 13.6. (Bidder 1)