Unit Cost Entry
Unit Cost Element - CCTV Video Camera Assembly
Unit Cost Component - Remove Pole Mounted Camera
Elgin, Illinois, United States
Description
Remove CCTV Camera. Maintenance to accommodate roadway construction.
Cost Type
Bid TabulationData Date
2013Reported Units
10Units
Each (EA)Year (Dollars)
2016Capital Cost per Unit ($)
O & M Cost per Unit ($)
$1,778.00Lifetime
yearsNotes
Project Description: Advance Intelligent Transportation Systems (ITS) Relocation - Jane Addams Memorial Tollway (I-90) - Mile Post 54.2 to Mile Post 79.5 - Station 2823+00 to Station 4133+00 (Bidder 3)Related Unit Cost Subsystems
Keywords
None defined
ID: 2017-05153