Cost

Implementing Integrated Corridor Management (ICM) strategies on the I-15 Corridor in San Diego, California is estimated to cost $1.42 million annualized and a total 10-year life-cycle cost of $12 million.

Cost estimates from the analysis, modeling, and simulation of ICM strategies implemented in the I-15 Corridor in San Diego, California.


September 2010
San Diego; California; United States


Summary Information

Interstate 15 (I-15) is a north–south Interstate Highway that runs from San Diego, California, to the Canadian border. I-15 is a major corridor in San Diego that services commuting trips, regional traffic, and interstate and international commercial vehicles, and one of the pioneer sites in the USDOT's Integrated Corridor Management (ICM) Initiative. To estimate the benefits and costs associated with implementing ICM on the corridor, a study followed the USDOT Analysis, Modeling and Simulation (AMS) framework to assess the impacts of ICM strategies on mobility under high, medium, and low travel demand, daily operations, and freeway and arterial incidents. The assessed ICM strategies included pretrip and en-route traveler information, mode shift to transit, freeway ramp metering, signal coordination on arterials with freeway ramp metering, physical bus priority, and congestion pricing on managed lanes.

The study estimated the capital, operating and maintenance (O&M) and annualized costs for the ICM strategies. Capital costs are up-front costs needed to procure and install ICM equipment. O&M costs are the continuing costs necessary to operate and maintain the deployed equipment including labor costs. Annualized costs are the average annual costs of deploying, operating, and maintaining ICM; annualized costs are especially useful when estimating long-term budgetary impacts of ICM projects. Annualized costs are determined from capital costs that have been amortized over the anticipated life of each piece of equipment.

Findings
  • A total 10-year life-cycle project cost of $12.0 million
  • An annualized cost of $1.42 million over the 10 year project life cycle


System Cost Comments

No comments posted to date

Comment on this System Cost

To comment on this summary, fill in the information below and click on submit. An asterisk (*) indicates a required field. Your name and email address, if provided, will not be posted, but are to contact you, if needed to clarify your comments.



Source

Integrated Corridor Management: Analysis, Modeling, and Simulation for the I-15 Corridor in San Diego, California

Author: Cambridge Systematics

Published By: U.S. DOT

Prepared by Cambridge Systematics for the U.S. DOT

Source Date: September 2010

EDL Number: Forthcoming

URL: http://www.its.dot.gov/icms/pioneer_sdiego.htm

System Cost

$12 million over the 10-year project life cycle